We have started the implementation of the project “Reconstruction and expansion of the water treatment plant in Brzozów Stary”, which includes:

  • construction of a container water treatment plant with a capacity of 78 m³/h;
  • construction of a treated water tank with a capacity of 500 m³;
  • construction of tanks for rinsing water;
  • construction of inter-facility networks: water supply, sanitary sewage, storm sewage, technological sewage, electrical and telecommunications;
  • replacement of well casings;
  • construction of a new exit from the district road to the facility;
  • hardening of the area including the construction of internal communication routes and land development;
  • replacement of existing fence. 

According to the agreement, the entire task is to be completed by November 2022. 