The Water Treatment Plant in Bożęcin is another of our lightweight frame plants. The plant has a capacity of 50 m³/d and can be expanded to 100 m³/d. Our mobile container plant was used during construction to ensure residents wouldn't experience water shortages or deterioration in water quality during the project. The project was implemented using the design-build formula, meaning Proffico was responsible for developing design documentation, obtaining approvals and permits, and carrying out construction and assembly work. Our flagship construction manager, Paweł, completed the entire project in 14 months!